The Tuktoyaktuk Erosion Mitigation Project began construction in March 2024 to address ongoing coastal erosion impacting critical shoreline areas. The project covered four key sites and additional armoring was completed, including:
Through Challenger’s Indigenous Partnership, Inukshuk Geomatics, we were able to support both the original survey for design with Baird Engineering, ongoing construction layout and ongoing monitoring.
Project Duration: 2024-2026
Project Manager: Marshall Hatton
Project Staff: Geoff Anderson, Adam Bursey and Chris Sobolewski
Approximate Hours: Approx. 6000 hrs.
Inukshuk Geomatics delivered integrated geomatics services including GNSS, bathymetric surveying, and UAV data to model both the ocean floor and rapidly changing shorelines both pre-construction and during mitigation. Geotechnical instrumentation, including ERT (Electrical Resistivity Tomography) and thermistor cables laid out and their positions recorded once installed to monitor permafrost response beneath newly constructed layers. Due to continuous erosion, survey data had to be refreshed regularly, ensuring accurate design updates and construction execution.
Project Priority (Put these in order of most important to least important)
Rapid coastal erosion which is reaching 1–2 meters per year due to thawing permafrost, longer ice-free seasons, and stronger storms was putting homes, infrastructure, and culturally important sites at risk. Inukshuk Geomatics supported the solution by delivering accurate, up-to-date survey data that informed design, guided construction, and ensured shoreline protection measures were built in the right place, at the right elevation, despite constantly changing ground conditions. This mitigation project was designed to help the community protect their land.
Working in a sensitive Arctic environment meant construction was limited to winter conditions to minimize ground disturbance and avoid instability from thawing permafrost. Which meant our team was working in the high arctic from November to March.
The project relied on close, ongoing communication between field crews, site supervisors, project managers, and the engineering design teams. Inukshuk Geomatics worked directly with E Grubens Transport and their specialized revetment construction crews from southern British Columbia, collaborating in real time with equipment operators and supporting quality control inspections to ensure work aligned with design intent.